Diesel Defence fuel polishing preserves power for Scottish islanders

A fuel cleaning operation identified thick layers of sludge at the bottom of SSE’s two 1,000,000-litre bulk storage tanks. The contamination threatened the reliability of the entire power station. Arnish provides top-up power for the Isle of Lewis. The island’s 20MW cable supply from the mainland does not meet the peak demand of 27MW.
If contaminated fuel caused the power station’s generators to fail, islanders would face brownouts or blackouts. SSE had to take action.
“The filters were coming out black”
The contamination in Arnish’s fuel stocks was evident without the need for a fuel test. When they were removed, spent filters were black and clogged with solid particulate and microbial contamination.
Each filter was meant to last 500 hours. At one point they were being replaced in less than 48. Maintenance had become costly and time-consuming.
Fuel starvation
On occasion, clogged filters had a more calamitous effect than increasing SSE’s maintenance workload. The modern, high-speed engines used at Arnish require high and consistent fuel pressure. If a clogged filter threatened this during the day, staff could change the filter as soon as they saw an alert.
But there are no staff at the site at night. Clogged filters had sometimes starved the generators of fuel and caused a shutdown.
The demand for fuel polishing
SSE initially commissioned IPU to perform a ClearTank fuel cleaning. This was only a short-term solution. IPU removed the contamination from the tanks but it was bound to return because the fuel spent so many months in storage.
The Isle of Lewis’ climate exacerbated the problem. Big changes in temperature and humidity provide an ideal environment for contaminants to develop. SSE concluded the only solution was to install a fixed fuel polishing unit that would keep their fuel clean 24/7.
The solution
SSE commissioned IPU to design and build an on-tank fuel polishing unit to resolve its contamination issues. They were already impressed by IPU’s capabilities having previously installed three small Diesel Defence polishers to service the site’s day tanks.
The brief was to fabricate a bespoke polishing system that would connect permanently to SSE’s two bulk storage tanks and fit the site’s existing infrastructure. The goal demanded was to rapidly and efficiently recirculate 2 million litres of fuel to keep it free of contamination and safeguard Lewis’ electricity supply.
IPU’s experienced engineering team worked closely with SSE’s staff to ensure the unit matched the client’s exact specifications.
The result
IPU’s Diesel Defence polishing unit immediately addressed the severe contamination affecting the station’s fuel
tanks.
The unit runs 24/7. Recirculation repeatedly cleans the fuel and prevents pockets of dirty fuel and water from collecting in stagnant parts of the tanks. Multi-stage filtration and exceptional flow rates of up to 1,000lpm rapidly remove particulates, water content and microbial growth.
SSE’s fuel stocks now exceed industry cleanliness standards such as ISO4406 and EN590. The operational pressures on SSE’s workforce have eased significantly. The Diesel Defence unit is a ‘fit and forget’ solution. It runs unassisted month after month. The site is attended on a daily basis but SSE’s staff no longer have to change filters nor do they have to check the Diesel Defence unit. It alerts them if it needs any attention.
Prior to the Diesel Defence installation, staff had to change filters on one of the station’s eight engines every day. After IPU’s intervention there was a period of two months when no filters needed replacing. When they are changed as part of a standard maintenance schedule, the spent filters are visibly cleaner.
Thanks to IPU’s solution, SSE’s employees have more time to focus on more constructive aspects of their business. There have been no fuel-related engine shutdowns since the Diesel Defence unit was installed. The generators have been continually available to serve the islanders.
IPU’s solution has established the reliability the power station needed and reduced maintenance to a level SSE can accept.
“It was a complex installation but everything was conducted smoothly and on time.”
Roddy Graham, Station Manager – SSE